Shilpriya Builders And Developers

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Silicon EnclaveP51800007484Kurla2017Not reported31 Dec 201930 Oct 2020+10 months
Silicon Hofe A WingP51800029560Kurla2021Not reported30 Jun 2024—On date
Silicon HeritageP51800046689Kurla2022Not reported31 Dec 2025—On date
Silicon Hofe B WingP51800054852Chembur2024Not reported30 Sep 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Silicon Enclave+10 mo
  • Silicon Hofe A WingOn date
  • Silicon HeritageOn date
  • Silicon Hofe B WingOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 10 months, for Silicon Enclave (P51800007484).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology