Shewalkar Developers Limited

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+52 moMedian delayvs RERA proposed date · 3 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Multani ApartmentP50500006543Nagpur (M Corp.)2017Not reported31 Mar 20191 Jan 2026+82 months
Shewalkar Lake-ViewP50500008244Nagpur (M Corp.)2017Lapsed31 Dec 201830 Sep 2024+69 months
Ram Shewalkar ParisarP51000009928Wani (M Cl)2017Lapsed15 Apr 2026—On date
Shewalkar ArcadeP50500009130Nagpur (M Corp.)2017Not reported31 Dec 201730 Oct 2020+34 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Multani Apartment+82 mo
  • Shewalkar Lake-View+69 mo
  • Ram Shewalkar ParisarOn date
  • Shewalkar Arcade+34 mo

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 82 months, for Multani Apartment (P50500006543).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology