Shewalkar Developers Limited
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+52 moMedian delayvs RERA proposed date · 3 extended
2Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Multani ApartmentP50500006543 | Nagpur (M Corp.) | 2017 | Not reported | 31 Mar 2019 | 1 Jan 2026 | +82 months |
| Shewalkar Lake-ViewP50500008244 | Nagpur (M Corp.) | 2017 | Lapsed | 31 Dec 2018 | 30 Sep 2024 | +69 months |
| Ram Shewalkar ParisarP51000009928 | Wani (M Cl) | 2017 | Lapsed | 15 Apr 2026 | — | On date |
| Shewalkar ArcadeP50500009130 | Nagpur (M Corp.) | 2017 | Not reported | 31 Dec 2017 | 30 Oct 2020 | +34 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 82 months, for Multani Apartment (P50500006543).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: RAM SHEWALKAR PARISAR (Regulatory Case No. 396 OF 2025) dated 10 March, 2026. · Ram Shewalkar Parisar · P51000009928 · 10 Mar 2026
- DeregisteredDeregistered: MULTANI APARTMENT · Multani Apartment · P50500006543
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology