Sheth Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Beverly Hills - Building FP52100008510Hinjavadi (Ct)2017Certificate Signed31 Mar 202030 Mar 2022+24 months
Times SquareP52100009391Hinjavadi (Ct)2017Certificate Signed31 Dec 201731 Dec 2018+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Beverly Hills - Building F+24 mo
  • Times Square+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Beverly Hills - Building F (P52100008510).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology