Shantee Realty And Life Space

Company or firm · 6 projects · 6 MahaRERA registrations

6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Spanish ResidencyP99000001765Vasaivirar City (M Corp)2017Not reported31 Mar 2019—On date
Marvel HeightsP99000026982Vasaivirar City (M Corp)2020Not reported30 Jun 2025—On date
Spanish VillaP99000029046Vasaivirar City (M Corp)2021Not reported31 Dec 2025—On date
Spanish VillaP99000029785Vasaivirar City (M Corp)2021Not reported31 Dec 2027—On date
Srishti HeightsP99000056001Vasaivirar City (M Corp)2024Not reported31 Dec 2028—On date
Flamingo ResidencyP99000076599Vasaivirar City (M Corp)2024Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Spanish ResidencyOn date
  • Marvel HeightsOn date
  • Spanish VillaOn date
  • Spanish VillaOn date
  • Srishti HeightsOn date
  • Flamingo ResidencyOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology