Shantee Homes Realty Llp
Company or firm · 6 projects · 8 MahaRERA registrations
Projects68 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%3 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sunshine Green Park Phase 2P99000001294 | Vasaivirar City (M Corp) | 2017 | Not reported | 31 Mar 2019 | 30 Jun 2025 | +75 months |
| Sunshine Green ParkP99000001370 | Vasai | 2017 | Not reported | 31 Mar 2018 | — | On date |
| Sunshine Green ParkP99000017859 | Vasai | 2018 | Not reported | 30 Jun 2022 | 31 Dec 2026 | +54 months |
| Spring FieldP99000020393 | Vasaivirar City (M Corp) | 2019 | Not reported | 28 Feb 2025 | 31 Dec 2030 | +70 months |
| Shamrock ResidencyP99000020998 | Vasaivirar City (M Corp) | 2019 | Not reported | 30 Apr 2024 | — | On date |
| Sunshine EnclaveP99000030524 | Vasai Virar City (M Corp) | 2021 | Not reported | 31 Dec 2027 | — | On date |
| Sunshine Green ParkP99000030553 | Vasai | 2021 | Not reported | 31 Dec 2025 | — | On date |
| Shalimar ResidencyP99000076607 | Vasai Virar City (M Corp) | 2024 | Not reported | 30 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 75 months, for Sunshine Green Park Phase 2 (P99000001294).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology