Shanmukhi Buildcon

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shanmukhi AlayamP52000054283Panvel2024Not reported30 Mar 2026—On date
Shanmukhi AnantaPM1270002600393Panvel2026Not reported30 Sep 2028—On date
Shanmukhi SpandaPM1270002602092Shedung2026Not reported31 Mar 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shanmukhi AlayamOn date
  • Shanmukhi AnantaOn date
  • Shanmukhi SpandaOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology