Shalini Shivaji Pawar

Individual promoter · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+83 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shiv Shahi ComplexP51700015735Narayangaon2018Certificate Signed30 Jun 201931 Dec 2025+78 months
Shiv Shahi ComplexP51700017015Narayangaon2018Certificate Signed30 Dec 202231 Mar 2030+87 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shiv Shahi Complex+78 mo
  • Shiv Shahi Complex+87 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 87 months, for Shiv Shahi Complex (P51700017015).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology