Shaheen Mansoor Bijali

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Swapnshilp PlazaP53000033062Ichalkaranji (M Cl)2022Certificate Signed31 Dec 202431 Dec 2024On date
Swapnshilp TowerP53000047148Ichalkaranji (M Cl)2022Certificate Signed30 Dec 202230 Dec 2024+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Swapnshilp PlazaOn date
  • Swapnshilp Tower+24 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Swapnshilp Tower (P53000047148).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology