Shah Housecon Private Limited
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 2 extended
2Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shah Business CentreP51800002825 | Borivali | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Shah Arcade IIIP51800003642 | Borivali | 2017 | Not reported | 30 Jul 2018 | 30 Jul 2019 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Shah Business Centre (P51800002825).
Regulatory cases across projects
- Listed as an NCLT insolvency projectListed as NCLT project: SHAH ARCADE III · Shah Arcade III · P51800003642
- Listed as an NCLT insolvency projectListed as NCLT project: Shah Business Centre · Shah Business Centre · P51800002825
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology