Seva Developers
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Yash ReidencyP51600012917 | Nashik | 2017 | Not reported | 31 Mar 2019 | — | On date |
| Suraj ParkP51600052435 | Satpur | 2023 | Not reported | 1 Jun 2027 | — | On date |
| Kiran VertexPM1220002601383 | Gangapur | 2026 | Not reported | 1 Jul 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology