Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Building No. 2 Wings A and B AlpineP51800000879Borivali2017Not reported30 Dec 2020—On date
Wing B of Composite Building No 1 Imperial EdgeP51900000723Ward Abcd2017Not reported30 Dec 2021—On date
Building No 3 Wing B AstronP51800001784Borivali2017Not reported30 Dec 202230 Jun 2023+6 months
Building No 3 Wing A EpsilonP51800004355Borivali2017Not reported30 Mar 2022—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Building No. 2 Wings A and B AlpineOn date
  • Wing B of Composite Building No 1 Imperial EdgeOn date
  • Building No 3 Wing B Astron+6 mo
  • Building No 3 Wing A EpsilonOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 6 months, for Building No 3 Wing B Astron (P51800001784).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology