Satyam Ventures Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gami Satyam Business AvenueP51700052956Navi Mumbai (M Corp.)2023Certificate Signed31 Dec 202730 Apr 2028+4 months
Gami Satyam PalacioP52000056145Kharghar2024Certificate Signed31 Dec 202831 Dec 2028On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gami Satyam Business Avenue+4 mo
  • Gami Satyam PalacioOn date

Track record notes

  • Longest extension on record: 4 months, for Gami Satyam Business Avenue (P51700052956).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology