Satyam Constructions
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Satyam RajyogP52100002338 | Dhanori | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Jaymala Business CourtP52100002339 | Manjari Bk | 2017 | Certificate Signed | 5 Apr 2019 | 5 Apr 2019 | On date |
| Satyam Niranjani Tower 1,2,3 & 4P52100017871 | Hadapsar | 2018 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Satyam Rajyog (P52100002338).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology