Skip to content
Deedo home
Menu

Satu Realty

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Satu AuraP99000009278Palghar2017Not reported31 May 2018—On date
Satu Aura-Tower 2P99000023052Palghar2019Certificate Signed30 May 202330 May 2023On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Satu AuraOn date
  • Satu Aura-Tower 2On date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology