Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+25 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Siddhi Towers A WingP52100007014Pimpri Chinchawad (M Corp.)2017Certificate Signed31 Dec 201931 Jan 2023+37 months
Ganesh RoyalP52100010138Pimpri Chinchawad (M Corp.)2017Certificate Signed31 Dec 201731 Dec 2018+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Siddhi Towers A Wing+37 mo
  • Ganesh Royal+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 37 months, for Siddhi Towers A Wing (P52100007014).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.