Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VistaP51800045286Kurla2022Not reported31 Dec 2025—On date
Shriram NiwasP51800055053Mulund2024Certificate Signed30 Jun 202730 Oct 2027+4 months
Krishna HeightsPM1180002500085Mulund2025Not reported31 Dec 2028—On date
YugantPM1180002501885Mulund2025Not reported30 Jun 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VistaOn date
  • Shriram Niwas+4 mo
  • Krishna HeightsOn date
  • YugantOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Shriram Niwas (P51800055053).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.