Sarvoday Enterprises

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anandi HeightsP51800002161Kurla2017Not reported31 Dec 201930 Jun 2022+30 months
Mahavir AshishP51800003457Kurla2017Not reported31 Dec 2019—On date
Tatva ShilaP51800048784Mulund2023Not reported31 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anandi Heights+30 mo
  • Mahavir AshishOn date
  • Tatva ShilaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Anandi Heights (P51800002161).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology