Saroj Landmark Realty Llp

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Chandak StellaP51800014201Borivali2017Not reported30 Mar 2022—On date
UnicornP51800028365Andheri2021Not reported30 Jun 2026—On date
GreenairyP51800035093Borivali2022Not reported30 Jun 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Chandak StellaOn date
  • UnicornOn date
  • GreenairyOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology