Saraswati Buildcon

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Meera Park RoyaleP51700001561Ambarnath(M Cl)2017Certificate Signed1 Feb 202131 Jan 2022+11 months
Meera Park RoyaleP51700021675Ambarnath(M Cl)2019Certificate Signed30 Dec 202130 Dec 2021On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Meera Park Royale+11 mo
  • Meera Park RoyaleOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 11 months, for Meera Park Royale (P51700001561).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology