Sarang Krishna Venture

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sarang TulipP52000022531Vadghar (Ct)2019Not reported31 Jul 2023—On date
Sarang AsterP52000026001Vadghar (Ct)2020Not reported30 Mar 2024—On date
Sarang VerbenaP52000027554Vadghar (Ct)2020Not reported30 Apr 202431 Jul 2024+3 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sarang TulipOn date
  • Sarang AsterOn date
  • Sarang Verbena+3 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 3 months, for Sarang Verbena (P52000027554).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology