Saptashree Reality Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Saptashree HeightsP51700000837Thane (M Corp.)2017Certificate Signed31 May 201831 May 2018On date
Saptashree GaliciaP51700054273Kolshet2024Certificate Signed31 May 202830 Sep 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Saptashree HeightsOn date
  • Saptashree Galicia+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Saptashree Galicia (P51700054273).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology