Sanjay Vasantlal Gundecha

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+10 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Va.Na.Oak Trust SankulP52100021353Peth2019Certificate Signed30 Mar 202430 Mar 2024On date
Kanhaiya Business CentreP52100029024Pune (M Corp.)2021Certificate Signed1 Apr 202431 Dec 2025+20 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Va.Na.Oak Trust SankulOn date
  • Kanhaiya Business Centre+20 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 20 months, for Kanhaiya Business Centre (P52100029024).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology