Sanjay Shyamlal Vyas
Individual promoter · 4 projects · 5 MahaRERA registrations
4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Naman ViharP51500005043 | Aurangabad | 2017 | Certificate Signed | 31 May 2019 | 31 May 2019 | On date |
| Laxmi Tower -1P51500017617 | Aurangabad (M Corp.) | 2018 | Certificate Signed | 30 Jun 2021 | 30 Jun 2021 | On date |
| Nikunj NagarP51500026408 | Aurangabad (M Corp.) | 2020 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Nikunj NagarP51500033660 | Aurangabad (M Corp.) | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Shital NagarP51500048680 | Aurangabad (M Corp.) | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Nikunj Nagar (P51500033660).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology