Sanjay Shyamlal Vyas

Individual promoter · 4 projects · 5 MahaRERA registrations

4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Naman ViharP51500005043Aurangabad2017Certificate Signed31 May 201931 May 2019On date
Laxmi Tower -1P51500017617Aurangabad (M Corp.)2018Certificate Signed30 Jun 202130 Jun 2021On date
Nikunj NagarP51500026408Aurangabad (M Corp.)2020Certificate Signed30 Jun 202430 Jun 2024On date
Nikunj NagarP51500033660Aurangabad (M Corp.)2022Certificate Signed31 Dec 202630 Apr 2027+4 months
Shital NagarP51500048680Aurangabad (M Corp.)2023Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Naman ViharOn date
  • Laxmi Tower -1On date
  • Nikunj NagarOn date
  • Nikunj Nagar+4 mo
  • Shital Nagar+4 mo

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Nikunj Nagar (P51500033660).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology