Sandesh Bhivsan Wagh
Individual promoter · 3 projects · 3 MahaRERA registrations · 1 reported completed
3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Meera SquareP51500008177 | Aurangabad (M Corp.) | 2017 | Completed | 28 Feb 2021 | — | On date |
| Jay-Shankar TowerP51500031303 | Satara (Ct) | 2021 | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Belpatra VillasP51500066511 | Satara (Ct) | 2024 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Belpatra Villas (P51500066511).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology