Samruddhi Developers
Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed
3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Riddhesh HeightsP51600012650 | Nashik | 2017 | Completed | 31 Mar 2018 | 31 Mar 2019 | +12 months |
| Suvarnagoda SankulP51600025825 | Nashik (M Corp.) | 2020 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Shree Trimbakraj HeightsP51600030652 | Nashik (M Corp.) | 2021 | Certificate Signed | 25 May 2024 | 25 May 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Riddhesh Heights (P51600012650).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology