Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Arihant HeightsP52100015353Pimpri Chinchawad (M Corp.)2018Certificate Signed31 Dec 201931 Dec 2019On date
Emerald TowersP52100032827Pimpri Chinchawad (M Corp.)2022Certificate Signed30 Jun 202631 Mar 2027+9 months
Radhaa Krishna HeightsP52100078777Pimpri Chinchawad (M Corp.)2025Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Arihant HeightsOn date
  • Emerald Towers+9 mo
  • Radhaa Krishna Heights+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 9 months, for Emerald Towers (P52100032827).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology