Samir Mahamad Ghare

Individual promoter · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+11 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Royal ParkP52800017643Lanja (Ct)2018Certificate Signed30 Jun 202130 Dec 2022+18 months
MarigoldP52800022149Lanja (Ct)2019Not reported30 Dec 202131 Dec 2026+60 months
Marigold 2P52800054238Lanja (Ct)2024Not reported31 Dec 2026—On date
Elite ParkP52800078154Lanja (Ct)2024Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Royal Park+18 mo
  • Marigold+60 mo
  • Marigold 2On date
  • Elite Park+4 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 60 months, for Marigold (P52800022149).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology