Sambhav Homes

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Deep ElanzaP52000018851Karanjade2018Certificate Signed30 Dec 202230 Dec 2022On date
Deep VisionaireP52000019992Panvel2019Certificate Signed30 Mar 202329 Mar 2024+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Deep ElanzaOn date
  • Deep Visionaire+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Deep Visionaire (P52000019992).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology