Samarttha Trimurti Properties

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+15 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
41 EsteraP52100003574Punawale2017Certificate Signed31 Jul 201830 Apr 2019+9 months
41 EsteraP52100014226Punawale2017Certificate Signed27 Mar 20221 Nov 2023+20 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 41 Estera+9 mo
  • 41 Estera+20 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 20 months, for 41 Estera (P52100014226).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology