Sajid Abdul Latif Bhatkar

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Taj ResidencyP52800005530Ratnagiri (M Cl)2017Not reported21 Aug 2019—On date
Zainabbi Mohammad Patankar ResidencyP52800014918Ratnagiri (M Cl)2018Certificate Signed15 Jul 202114 Jan 2023+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Taj ResidencyOn date
  • Zainabbi Mohammad Patankar Residency+18 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Zainabbi Mohammad Patankar Residency (P52800014918).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology