2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Cloud 11P52100007087Charholi Kh2017Certificate Signed31 Dec 201831 Dec 2018On date
Kundan AlturaP52100027123Pimpri Chinchawad (M Corp.)2020Certificate Signed30 Jun 202430 Nov 2024+5 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Cloud 11On date
  • Kundan Altura+5 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 5 months, for Kundan Altura (P52100027123).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.