Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
New Sailee HeritageP51800017631Borivali2018Certificate Signed29 Oct 202929 Oct 2029On date
Prathamesh GalaxyP51800018914Kurla2018Certificate Signed30 Dec 202630 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • New Sailee HeritageOn date
  • Prathamesh GalaxyOn date

Track record notes

    Regulatory cases across projects

    SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology