Sai Proviso Homes
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Leisure Town Phase 1P52100002395 | Hadapsar | 2017 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Leisure Town Phase 2P52100026621 | Hadapsar | 2020 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Leisure Town Phase 2 (P52100026621).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: LEISURE TOWN PHASE 1 (Regulatory Case No. 384 OF 2025) dated 30 June, 2025. · Leisure Town Phase 1 · P52100002395 · 30 Jun 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology