Sai Essen Properties

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+3 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aishwaryam Courtyard IIP52100000799Haveli2017Not reported31 Dec 202130 Jun 2022+6 months
Aishwaryam NivaaraP52100016005Pimpri Chinchawad (M Corp.)2018Not reported30 Sep 202030 Jun 2022+21 months
Aishwaryam MelodyP52100024765Pimpri Chinchawad (M Corp.)2020Not reported25 Feb 2020—On date
Aishwaryam Courtyard GoldP52100049086Chikhali2023Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aishwaryam Courtyard II+6 mo
  • Aishwaryam Nivaara+21 mo
  • Aishwaryam MelodyOn date
  • Aishwaryam Courtyard GoldOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 21 months, for Aishwaryam Nivaara (P52100016005).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology