Sai Essen Properties
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+3 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Aishwaryam Courtyard IIP52100000799 | Haveli | 2017 | Not reported | 31 Dec 2021 | 30 Jun 2022 | +6 months |
| Aishwaryam NivaaraP52100016005 | Pimpri Chinchawad (M Corp.) | 2018 | Not reported | 30 Sep 2020 | 30 Jun 2022 | +21 months |
| Aishwaryam MelodyP52100024765 | Pimpri Chinchawad (M Corp.) | 2020 | Not reported | 25 Feb 2020 | — | On date |
| Aishwaryam Courtyard GoldP52100049086 | Chikhali | 2023 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 21 months, for Aishwaryam Nivaara (P52100016005).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology