Sai Datta Enterprises

Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Saidatta Paradise Wing AP52100014071Nanekarwadi (Ct)2017Not reported30 Jun 202130 Dec 2022+18 months
Saidatta ParadiseP52100014072Nanekarwadi (Ct)2017Not reported31 May 2019—On date
Saidatta ParadiseP52100050847Nanekarwadi (Ct)2023Not reported31 Dec 2028—On date
Dwarkadhish Park Building DP52100054421Chakan (Ct)2024Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Saidatta Paradise Wing A+18 mo
  • Saidatta ParadiseOn date
  • Saidatta ParadiseOn date
  • Dwarkadhish Park Building DOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Saidatta Paradise Wing A (P52100014071).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology