Sai Buildcon

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai BuildconP52100012551Pimpri Chinchawad (M Corp.)2017Not reported31 Dec 201831 Dec 2025+84 months
Sai GalaxyP52100029391Thergaon2021Not reported28 Feb 2024—On date
Sai AudumbarP52100034097Punawale2022Not reported31 Dec 202331 Dec 2024+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Buildcon+84 mo
  • Sai GalaxyOn date
  • Sai Audumbar+12 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 84 months, for Sai Buildcon (P52100012551).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology