Sai Angan Projects Llp
Company or firm · 2 projects · 4 MahaRERA registrations
Also appears as M/S Sai Angan Projects Llp
2Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai EmpireP52100049242 | Wadmukhwadi | 2023 | Not reported | 31 Dec 2023 | — | On date |
| Sai EmpireP52100049766 | Wadmukhwadi | 2023 | Not reported | 31 Dec 2023 | — | On date |
| Plot DP52100055776 | Wadmukhwadi | 2024 | Not reported | 31 Aug 2024 | 31 Mar 2025 | +7 months |
| Sai EmpireP52100078973 | Wadmukhwadi | 2025 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 7 months, for Plot D (P52100055776).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology