Sahyadri Properties

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aboli, Madhuban Phase 4P52100000877Kirkatwadi2017Certificate Signed4 Jan 20194 Jan 2019On date
TanishqP52100001450Pune (M Corp.)2017Certificate Signed31 Jul 201831 Jul 2019+12 months
Parijatak, Madhuban Phase 5P52100010997Kirkatwadi2017Certificate Signed30 Sep 201929 Oct 2021+25 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aboli, Madhuban Phase 4On date
  • Tanishq+12 mo
  • Parijatak, Madhuban Phase 5+25 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 25 months, for Parijatak, Madhuban Phase 5 (P52100010997).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology