Sagar Mahadev Kate
Individual promoter · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kate prideP52100009632 | Jalochi | 2017 | Certificate Signed | 10 Jun 2018 | 10 Jun 2018 | On date |
| Moraya palaceP52100013003 | Baramati Rural | 2017 | Certificate Signed | 24 Jan 2019 | 24 Jan 2019 | On date |
| Kate prideP52100013121 | Jalochi | 2017 | Certificate Signed | 21 Feb 2019 | 21 Feb 2019 | On date |
| Kate cityP52100013834 | Rui | 2017 | Certificate Signed | 1 Nov 2019 | 1 Nov 2019 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology