Sagar Mahadev Jarad

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+27 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Dattakrupa ApartmentP52700033368Khandala2022Certificate Signed10 Jan 202530 Jun 2029+53 months
Snehsagar ApartmentP52700045366Shirwal2022Certificate Signed29 Apr 202629 Apr 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dattakrupa Apartment+53 mo
  • Snehsagar ApartmentOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 53 months, for Dattakrupa Apartment (P52700033368).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology