Sagar Constructions

Company or firm · 4 projects · 4 MahaRERA registrations · 3 reported completed

4Projects4 RERA registrations
3Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anand SagarP51600011939Nashik (M Corp.)2017Completed31 Dec 2017—On date
Sukh SagarP51600012549Nashik (M Corp.)2017Certificate Signed31 Mar 201831 Mar 2018On date
Shri Shri SagarP51600012595Nashik (M Corp.)2017Completed14 Feb 2018—On date
Sukhsagar NxP51600012739Nashik (M Corp.)2017Completed5 Jan 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anand SagarOn date
  • Sukh SagarOn date
  • Shri Shri SagarOn date
  • Sukhsagar NxOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology