Sagar Constructions
Company or firm · 4 projects · 4 MahaRERA registrations · 3 reported completed
4Projects4 RERA registrations
3Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Anand SagarP51600011939 | Nashik (M Corp.) | 2017 | Completed | 31 Dec 2017 | — | On date |
| Sukh SagarP51600012549 | Nashik (M Corp.) | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Shri Shri SagarP51600012595 | Nashik (M Corp.) | 2017 | Completed | 14 Feb 2018 | — | On date |
| Sukhsagar NxP51600012739 | Nashik (M Corp.) | 2017 | Completed | 5 Jan 2018 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.