Sadguru Developers
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sadguru Nakshtra Phase IP51700017067 | Titwala | 2018 | Not reported | 30 Dec 2023 | — | On date |
| Sadguru Nakshtra Phase IIP51700028547 | Kalyan | 2021 | Not reported | 30 Oct 2023 | 29 Oct 2024 | +12 months |
| Sadguru Nakshtra Phase IIIP51700053926 | Titwala | 2023 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Sadguru Nakshtra Phase II (P51700028547).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology