Sadguru Associate

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sadguru Harmony Ph-1 Wing AP51700004904Badlapur (M Cl)2017Certificate Signed31 Dec 201930 Dec 2021+24 months
Sadguru HarmonyP51700034459Badlapur (M Cl)2022Certificate Signed30 Jun 202630 Oct 2026+4 months
Sadguru HarmonyP51700034703Badlapur (M Cl)2022Certificate Signed30 Jun 202630 Oct 2026+4 months
The Address Wing C Phase IIIP51700050566Badlapur (M Cl)2023Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sadguru Harmony Ph-1 Wing A+24 mo
  • Sadguru Harmony+4 mo
  • Sadguru Harmony+4 mo
  • The Address Wing C Phase III+4 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Sadguru Harmony Ph-1 Wing A (P51700004904).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology