Sadanand Waman Patil
Individual promoter · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vatsalya ResidencyP52000011076 | Alibag | 2017 | Not reported | 28 Feb 2018 | — | On date |
| Vatsalya Residency Phase -IIP52000028084 | Ambepur | 2021 | Not reported | 30 Jun 2023 | 29 Jun 2024 | +12 months |
| Vatsalya Residency Building -2P52000033050 | Alibag | 2022 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Vatsalya Residency Phase -II (P52000028084).
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Mr. Sadanand Waman Patil (Suo Motu Case No. 112 of 2020) dated 20th February 2020 · Vatsalya Residency · P52000011076 · 20 Feb 2020
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology