Sabari Developers Llp

Company or firm · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%3 of 6 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sabari Palm ViewP51800001155Kurla2017Not reported31 Mar 2019—On date
Natekar HeightsP51800002547Kurla2017Not reported31 May 201930 Oct 2020+17 months
Sabari HorizonP51800003677Kurla2017Not reported31 May 201930 Oct 2020+17 months
Sabari ShobhaP51800003844Kurla2017Not reported30 Nov 202030 Nov 2021+12 months
Sabari HillgrangeP51800007070Kurla2017Not reported31 May 2019—On date
Sabari GayathriP51800028135Kurla2021Not reported30 Sep 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sabari Palm ViewOn date
  • Natekar Heights+17 mo
  • Sabari Horizon+17 mo
  • Sabari Shobha+12 mo
  • Sabari HillgrangeOn date
  • Sabari GayathriOn date

Track record notes

  • 3 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 17 months, for Natekar Heights (P51800002547).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology