S2 Realty And Developers Private Limited

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+48 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
DiscoveryP52100002302Kune N.M.2017Certificate Signed31 Oct 201831 Mar 2023+53 months
DiscoveryP52100012273Kune N.M.2017Certificate Signed30 Sep 202030 Sep 2024+48 months
Discovery Phase - IiiaP52100017802Kune N.M.2018Not reported30 Dec 202230 Jun 2024+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Discovery+53 mo
  • Discovery+48 mo
  • Discovery Phase - Iiia+18 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 53 months, for Discovery (P52100002302).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology