Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
S S ParkP51500007039Aurangabad (M Corp.)2017Certificate Signed31 Mar 201931 Mar 2019On date
S S Park Phase 2P51500008157Aurangabad (M Corp.)2017Completed31 Mar 2019—On date
S S Park Ist PhaseP51500012611Aurangabad (M Corp.)2017Certificate Signed31 Mar 201831 Mar 2018On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • S S ParkOn date
  • S S Park Phase 2On date
  • S S Park Ist PhaseOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology