Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
S R K CornerP52100015443Pimpale Gurav2018Not reported30 Sep 2020—On date
Rajgad 3P52100020606Pimpri Chinchawad (M Corp.)2019Not reported30 Dec 2023—On date
Rajgad 5P52100024020Pimpri Chinchawad (M Corp.)2020Not reported30 Mar 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • S R K CornerOn date
  • Rajgad 3On date
  • Rajgad 5On date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology