S.K.Construction
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as S. K. CONSTRUCTION
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Odhav BaugP51800011780 | Kurla | 2017 | Certificate Signed | 30 Sep 2018 | 30 Sep 2018 | On date |
| S.K.Milan ResidencyP51800022943 | Kurla | 2019 | Certificate Signed | 30 Mar 2023 | 29 Mar 2024 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for S.K.Milan Residency (P51800022943).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus M/s S. K. Construction (Suo Motu Case No. 33 of 2019) dated 17th December 2019 · Odhav Baug · P51800011780 · 17 Dec 2019
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology