Rushikesh Bhaguji Zore
Individual promoter · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+20 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Divine ResidencyP52000021595 | Vadghar (Ct) | 2019 | Certificate Signed | 30 Jun 2022 | 1 Feb 2024 | +20 months |
| Divine PlazaP52000023624 | Wahal | 2019 | Certificate Signed | 30 Dec 2022 | 31 May 2025 | +29 months |
| Divine HomeP52000023971 | Vadghar (Ct) | 2020 | Certificate Signed | 30 Dec 2022 | 30 Dec 2023 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 29 months, for Divine Plaza (P52000023624).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology